    Deploy new version of grains

    Rolling upgrade

    In this method you deploy newer silos directly on your environment. This is the simplest method, but it can be difficult to interrupt an ongoing deployment and to rollback.

    Recommended configuration:

    • DefaultCompatibilityStrategy set to BackwardCompatible
    • DefaultVersionSelectorStrategy set to AllCompatibleVersions
    var silo = new SiloHostBuilder()
      [...]
      .Configure<GrainVersioningOptions>(options => 
      {
        options.DefaultCompatibilityStrategy = nameof(BackwardCompatible);
        options.DefaultVersionSelectorStrategy = nameof(AllCompatibleVersions);
      })
      [...]
    

    When using this configuration, "old" clients will be able to talk to activations on both versions of silos. Newer clients and silos will only trigger new activations on newer silos.

    Rolling gif

    Using a staging environment

    In this method you will need a second environment (Staging environment), on which you will deploy newer silos before stopping the Production environment. The Production and the Staging silos and clients will be part of the same cluster. It is important that silos from both environment can talk to each other.

    Recommended configuration:

    • DefaultCompatibilityStrategy set to BackwardCompatible
    • DefaultVersionSelectorStrategy set to MinimumVersion
    var silo = new SiloHostBuilder()
      [...]
      .Configure<GrainVersioningOptions>(options => 
      {
        options.DefaultCompatibilityStrategy = nameof(BackwardCompatible);
        options.DefaultVersionSelectorStrategy = nameof(MinimumVersion);
      })
      [...]
    

    Suggested deployment steps:

    1. "V1" silos and clients are deployed and are running in the Production slot.
    2. "V2" silos and clients begin to start in the Staging slot. They will join the same cluster as the Production slot. No "V2" activations will be created so far.
    3. Once the deployment in the Staging slot is finished, the developper can redirect some traffic on the V2 clients (smoke tests, targeted beta users, ect.). This will create V2 activations, but since Grains are backward compatibles and that all silos are in the same cluster, no duplicate activations will be created.
    4. If the validation is successful, proceed to VIP swap. If not, you can safely shutdown the Staging cluster: existing V2 activations will be destroyed and V1 activations will be created if needed.
    5. V1 activations will naturally "migrate" to V2 silos eventually. You can safely shutdown V1 silos.
    Warning

    Remember that stateless workers are not versioned and that streaming agents will also start in the staging environment.

    • Improve this Doc
    Back to top Generated by DocFX